In January 2023, Council of Ministers supported the immediate progress to enable the 2026 delivery target for a 20MW onshore windfarm, as well as 10MW solar deployed across rooftops and car parks on the public estate to meet the target outlined in the Island Plan.

Manx Utilities reports identified in the timeline are available in the sections below.

In 2022, a survey of the entire Island (including public and private land) was carried out by Bureau Veritas, utilising the GIS maps which are publicly available in tandem with Manx Utilities’ 33kV and 11kV Transmission and Distribution networks. There are over 500 sites on the Isle of Man which are owned by the public estate. Note that this study was carried out in tandem with a study to identify suitable sites on public estate for the deployment of solar panels.

Bureau Veritas applied their own modelling to the GIS data to combine the locations with NOABL (a global wind data set) wind speeds for the Island as provided by Ronaldsway Meteorological Office, the prevailing wind direction (South West), access of a site to the prevailing wind direction, the locations of buildings, topography of the site, transport access and crucially the environmental and ecological maps which are publicly available.

Each of these areas are equally important however there are some hard constraints:

  • Wind speeds must be >6 m/s to ensure the windfarm is commercially viable. Typically on the Isle of Man these are all upland areas.
  • Wind turbines must be located a minimum of 500m from the nearest property in line with Technical Advice Note 8 (TAN 8) (England & Wales) to mitigate noise impact.
  • Heathland should be avoided where possible due to the high net biodiversity value of the land; the upland areas which do not have heathland are typically all catchment areas for water.
  • The local network must be capable of supporting a 20MW generation input.

Once these key areas are considered our iterative selection process has indicated there are three broad areas on the Isle of Man where windfarms can be accommodated. The public estate owns the majority of the upland areas, which are not heathland habitat because they are also catchment areas for reservoirs.

2022 Renewable Feasibility Study Redacted

In January 2023, Procurement specialists, Bird & Bird, presented their Procurement Report on the Isle of Man Onshore Renewables Project. Bird & Bird partnered with engineering consultants, Mott McDonald for the project.  The report identified the procurement and ownership routes which delivered the best value to customers of the Isle of Man. The report also provided a recommendation on the most suitable mix of renewables for the Isle of Man based on weather data and demand and resultant cost to customers. This report highlighted that the ownership route which resulted in the best value to customer was public ownership. It also recommended that the Isle of Man Government should commit to a 20MW onshore windfarm to meet its 2026 Target with smaller scale solar projects delivered through a Framework Approach across public buildings.

Bird & Bird highlighted that it would be necessary to utilise the onshore wind sites already identified to meet the 2026 Target.

2023 Procurement report Isle of Man Onshore renewables project redacted

Engineering consultants, WSP, were appointed in March 2022 to carry out a review of the Manx Utilities’ Future Generation Strategy and detailed network and commercial study to identify the limitations of the power system. This work was an extension of the work carried out in 2021 by the Isle of Man Government; the purpose was to validate some of the original outcomes and carry out more detailed network and commercial studies than had been completed previously.  The report identified the areas with the greatest strength for the connection of renewables to the power system and highlighted areas of the power system where 20MW could be accommodated. It also highlighted regions of the power system where there was a risk to the network from renewable connections.

All sites identified by Bureau Veritas have access to areas of the network which can accommodate 20MW onshore renewables. More detail is available on page 17 of the report.

2023 Future Energy Delivery Strategy

Environmental consultants, Wardell-Armstrong, were appointed in March 2023 to carry out the site-based feasibility studies for all three sites identified in the initial feasibility study.

The technical considerations relate to energy yield which can be delivered at each site, which is ultimately derived from wind speeds.

The feasibility studies cover the following areas:

  • Planning
  • Aviation & Telecommunications
  • Ecology
  • Landscape and Visual Impact Assessment
  • Noise
  • Transport
  • Heritage
  • Social
  • Water
  • Geotechnical
  • Air Quality
  • Peat

These surveys will provide the information we need to start the consultation process and it will also assist us in deciding which site will be taken forward to the Environmental Impact Assessment (EIA) stage. 

Phase 1 Report

Appendix 1 - Planning

Appendix 2 - Aviation & Telecommunication

Appendix 3 - Ecology

Appendix 4 - LVIA

Appendix 5 - Noise

Appendix 6 - Transport

Appendix 7 - Culture & Heritage

Appendix 8 - Social

Appendix 9 - Water

Appendix 10 - Geotechnical

Appendix 11 - Air Quality

Appendix 12 - Peat

 

Due to the strategic importance of decisions taken by Manx Utilities in relation to the decarbonisation of electricity supply on the Isle of Man, the Transition Programme has adopted the Operational Decision Making (ODM) process to support our decision making. Transition Programme Board to the Isle of Man and the high level of interest surrounding decarbonisation on-Island,

Two ODMs have now been completed for the onshore wind project to identify a site to take forward to the Environmental Impact Assessment stage.

An initial Operational Decision Making (ODM) exercise was held on 4th July to select a site to take forward to EIA on the information available. The ODM Team agreed that a third site, West Baldwin & Injebreck, should be ruled out on the basis it could not deliver on the 20MW target laid out in the Island plan

ODM - Onshore Wind Site Selection part 1

The ODM Team agreed to reconvene following completion of the Phase 1 report to select a preferred site from the remaining two options.

A second ODM was completed on 10th August following submission of the Phase 1 report.

The ODM Team decided that given the clear deliverability risk for Sulby, funding secured for the Environmental Impact Assessment was best spent at Earystane. None of the team members believed that Sulby would be deliverable by 2026 and given there was a clear recommendation from the consultants to select Earystane, it was unlikely that planning permission could be granted for Sulby.

The Environmental Impact Assessment stage will still consider alternative sites in support of the upcoming planning application, which will help to alleviate concerns about other possible sites.

It will not be possible to confirm that a 20MW windfarm at Earystane is deliverable until the completion of the Environmental Impact Assessments. The 12 month SODAR wind and noise measurements will begin in September 2023, which will provide some early reassurance in the EIA phase. There is no decision at this junction to progress with the delivery of a windfarm at Earystane, only to take this site forward to EIA.

ODM - Onshore Wind Project Site Selection - Part 2

Manx Utilities/Wardell Armstrong Scoping report and opinion

On the 15th February 2024 a Pre-Application Environmental Impact Assessment (EIA) Scoping report was submitted to the Department of the Environment, Food, and Agriculture (DEFA) in relation to the proposed Cair Vie Windfarm development at Earystane. Since submitting this Scoping report Manx Utilities and our contractor, Wardell Armstrong have continued to complete further surveys to update and optimise our designs for the windfarm.

This is often referred to as the scoping stage and scoping is a part of the overall planning process. Scoping ensures the correct information is included in the EIA and the follow up Environmental Statement (ES) which will accompany the Planning Application for public scrutiny and comment.

Although the Island Strategic Plan 2016 sets out clear policies for ‘when’ an EIA is required, it does not set out ‘how’ an EIA should be completed. The requirements for when an EIA are required are set out in the Island Strategic Plan 2016 and states that an onshore windfarm must have an EIA.

The Strategic Plan also states that current practice from England and Wales will be used to address ‘how’ an EIA should be completed and so the EIA will be completed in accordance with the requirements of the Town and Country Planning Act (Environmental Impact Assessment) England and Wales, 2017 regulations.

The Scoping report attempts to identify possible environmental impacts of any development which may be significant and which may require more detailed investigation within the EIA. This informs the drafting of an Environmental Statement for submission with the Planning Application.

The Scoping report also outlines the scope, methodology, and proposed approach of the EIA for assessing any impacts and identifies the stakeholder engagement process.

A Scoping opinion is produced and published by DEFA after consultation and technical input from statutory consultees on environmental issues within their specific areas.

The Scoping opinion is a written opinion clarifying the scope and level of detail to be provided in the Environmental Statement which will accompany the Planning Application. Responses in the Scoping opinion should also refer to the Town and Country Planning Act (Environmental Impact Assessment) England and Wales, 2017 regulations as referral to any other legislation might be considered outside the requirements of the Isle of Man Strategic Plan, 2016.

The Scoping opinion will be available on the IOM GOV website Cair Vie Wind Farm Project Scoping comments.

What happens Next?

The Scoping opinion provides technical input and feedback from statutory consultees on the Scoping report submitted earlier. Once published by DEFA, the Scoping opinion will be reviewed by Manx Utilities and its consultant Wardell Armstrong to ensure any further studies, surveys, technical information and requirements highlighted in the Scoping opinion are included in the Environmental Impact Assessment (EIA) where applicable.

The EIA will continue to progress for completion in May 2025, and will inform an Environmental Statement (ES) which will outline all significant environmental impacts and how these will be mitigated within the design of the Cair Vie windfarm at Earystane. The ES will then be submitted with the Planning Application for public scrutiny and comment as part of the planning process.

Scoping Report:

  1. Introduction
  2. Site Description
  3. Development Description
  4. Proposed Scope of the Environmental Statement
  5. Terrestrial Ecology
  6. Ornithology
  7. Marine Ecology
  8. Landscape and Visual
  9. Archaeology and Heritage
  10. Access, Traffic and Transport
  11. Noise and Vibration_Redacted
  12. Air Quality
  13. Ground Conditions
  14. Water Environment
  15. Climate Change and Resilience
  16. Materials and Waste
  17. Socio-Economics
  18. Human Health
  19. Aviation
  20. Electro-Magnetic Interference and Telecommunications
  21. Shadow Flicker
  22. Summary
  23. Appendix 2.1 Site Location Plan
  24. Appendix 3.1 Indicative Wind Turbine Layout Plan
  25. Appendix 3.2 Proposed Transport Routes Plan
  26. Appendix 5.1 Preliminary Ecological Appraisal Report_Redacted
  27. Appendix 7.1 Marine Ecology Reference List
  28. Appendix 8.1 Landscape Character Plan
  29. Appendix 9.1 Known Heritage Assets Plan
  30. Appendix 13.1 Phase 1 Desk Study Appendices_Redacted
  31. Appendix 13.1 Phase 1 Desk Study Drawings
  32. Appendix 13.1 Phase 1 Desk Study Report_Redacted
  33. Appendix 14.1 Water Environment Figures

 

 

In September 2023, the Environmental Impact Assessment (EIA) will commence. This piece of work will help us to identify how to mitigate the impact of our wind turbines on the local community and environment, as well as carrying out the design work. This work typically takes at least 18 months to allow for two seasons of bird and bat migrations. It also allows us to gather accurate wind speed data to ensure our turbine design will withstand the most extreme wind speeds at the sites.

More information will be provided as and when it becomes available.